GLAST The Gamma Ray Large Area Space Telescope

T&DF System Test Group

ISIS TRR Closure Plan

Done

Description of problem

Responsible party

Due date

Resolve PCI master abort

Steve Mazzoni/Ed Bacho

12-17-04

Upload ISIS FSW build*

Tony Waite

1-4-05

Test script: Routing of commands

Eric Hansen

12-17-04

LAT-DS-05398 (Acceptance Test)**

Jana Thayer/Susan Becker

1-6-05

JL-2, pin 2 not connected

Patrick Young

12-16-04

Test script: Ancillary, Attitude and Time Tone Commands

Eric Hansen

12-16-04

Test script: Boot Process

Eric Hansen

12-17-04

Test script: Reset Signal

Eric Hansen

12-17-04

LAT-DS-03541 (Safe Connection)

Jana Thayer/Susan Becker

12-16-04

LAT-DS-05297 (Grounding diagram)

Jana Thayer/Susan Becker

12-17-04

* Closure depends on #2 (resolution of PCI master abort)
** Closure depends on #4 - #8 (test script completion)
(SLAC has a two week shutdown: 12/18/04 - 1/2/05)