T&DF System Test Group meeting minutes (7/26/04)
Attending:
Jana, Susan, Larry, Gregg, Mark, Mike, Igor, Erick
Next meeting:
Monday, August 9, 2004 at 10AM.
1) Announcements for this week:
2) Upcoming/ongoing activity in the dataflow lab:
-
Testing of the ACD GASU has high (highest?) priority.
-
GASU production/testing will continue throughout the week.
-
Proto ISIS will be installed on the SIU test bench.
-
ES testing will proceed on the testbed with the help of the OSU folks.
-
FSW demo at 10:30 AM on Friday, July 30.
3) News (what everybody is working on):
Our test interface is finally ready for prime time! It is in CVS under ELX/GUI, so feel free to check it out and add your scripts to it. (TEM folks, this means you!) Some combination of Gregg, Amedeo, and Erick will try to add a power sequencing interface to the GUI. And I will try to get some documentation available for the GUI before the end of next week. How's that for ambitious?
Command/functional software tested on SIU. Test scripts written; single command sent between spacecraft and SIU. Would like more time on EPU/SIU. Time on this hardware will be difficult to get this week because Owen's ports are being installed, Dan Wood is in from NRL to learn how to work with a crate, and Jana is trying to upgrade/test new crate backplanes as they come in from the company. But next week is looking rosy.
4) SIU/EPU crate update:
5) ISIS
-
The hardware is collected on bench 1, which is becoming the ISIS development corner.
-
Waiting on a handful of cables before full out testing begins.
- ISIS FSW packages are being tested on the SIU crate on bench 1.
Thanks to Amedeo and Owen whose emails I purloined to write the blurbs about the new ports and LATTE4. Everyone is encouraged to use LATTE4 as much as possible, and to report all bugs/problems to Amedeo. As usual, thanks for all your hard work,
Jana
Minutes submitted by Jana Thayer.
|