LAT  Electronics, Data Acquisition & Instrument Flight Software

  Subsystem Manager:  Gunther Haller

Acceptance Test Data End Package and Reviews of SIU/EPU Modules

SIU Module ADTP Report Review Date/Time Notes
#1 PROTO LAT-TD-07583-01 (GLAT2508) PROTO Thur 11/17/05, 3:00pm, GLAST I, Bldg. 28  
#2 LAT-TD-07584-01 (GLAT2513) SIU
LAT-TD-07584-02 (GLAT2513) SIU
Thur 11/17/05, 3:00pm, GLAST I, Bldg. 28 Per NCR# 833, Rev. 2 was created to reflect the additional testing required for removal and rework of RAD750 board.
#3 LAT-TD-07585-01 (GLAT2527) SIU
LAT-TD-07585-02 (GLAT2527) SIU
Thur 11/17/05, 3:00pm, GLAST I, Bldg. 28
 
Per NCR# 833, Rev. 2 was created to reflect the additional testing required for removal and rework of RAD750 board.
#4 LAT-TD-07586-01 (GLAT2522) EPU
LAT-TD-07586-02 (GLAT2522) EPU
Thur 11/17/05, 3:00pm, GLAST I, Bldg. 28 Per NCR# 833, Rev. 2 was created to reflect the additional testing required for removal and rework of RAD750 board.
#5 LAT-TD-07587-01 (GLAT2523)
LAT-TD-07587-02 (GLAT2523)
Thur 11/17/05, 3:00pm, GLAST I, Bldg. 28 Per NCR# 833, Rev. 2 was created to reflect the additional testing required for removal and rework of RAD750 board.
#6 LAT-TD-07588-01 (GLAT2524) EPU
LAT-TD-07588-02 (GLAT2524) EPU
Mon 12/12/05, 1:00pm, GLAST I, Bldg. 28
 
Per NCR# 833, Rev. 2 was created to reflect the additional testing required for removal and rework of RAD750 board.
#7 LAT-TD-07590-01 (GLAT2526) TBD  
#8 LAT-TD-07589-01 (GLAT2525) TBD  

 

 

 

Back to the GLAST LAT Main Page