LAT Phase 1 Test Summary Report
Rev. 5PM 03/10/06 L.Wai
SIU EPU EPU Exec. Test Purpose P/F Notes Elapsed To Go
      LICOS S/C Monitoring without SIU through VSC EGSE checkout P   12 0
P       SIU-P flight mate, mate to EGSE temporarily install SIU-P P   12 0
P     LATTE PduGasuSelect - Primary Power-On verify we can test thru backdoor P   25 0
P     LATTE LAT401 acquire CAL CPT data P   0* 0
P     LATTE LAT501 acquire TKR CPT data P   0* 0
P     LATTE LAT301 acquire ACD CPT data     0* 0
  P0     EPU-P0 flight mate temporarily install EPU-P0 P   12 0
    P1   EPU-P1 flight mate install EPU-P1 P   12 0
P P0 P1 LICOS LAT001  power-on hardware config 1 P ACD not turned on 100 0
P P0 P1 LICOS LAT041 file uploads P   100 0
P P0 P1 LICOS LAT221  science ops P GARCs not enabled 25 0
P P0 P1 LICOS LAT011 power-off hardware config 1 P   25 0
R       SIU-R flight mate, mate to EGSE install SIU-R P cable tray issues 20 0
  R     EPU-R flight mate temporarily install EPU-R P   12 0
R R P1 LICOS LAT002 power-on hardware config 2 P misc. glitches 21 0
R R P1 LICOS LAT042 file uploads P misc. glitches 21 0
R R P1 LICOS LAT222 science ops P misc. glitches 21 0
R R P1 LICOS calu_pedestals_ci LCI test for CAL CPT     0 8
R R P1 LICOS calf_adc_p02 LCI test for CAL CPT     0 8
R R P1 LICOS TkrNoiseOccupancy LCI test for TKR CPT     0 8
R R P1 LICOS TkrReadingConfigurationTest LCI test for TKR CPT     0 8
R R P1 LICOS AcdPedestals LCI test for ACD CPT     0 8
R R P1 LICOS AcdTciRegRange LCI test for ACD CPT     0 8
R R P1 LICOS LAT402 CAL CPT     0 20
R R P1 LICOS LAT502 TKR CPT     0 20
R R P1 LICOS LAT302 ACD CPT     0 20
R R P1 LICOS LAT022 CPU re-initialization     0 12
R R P1 LICOS LAT152 thermal control system test     0 12
R R P1 LICOS LAT012 power-off hardware config 2     0 12
P       SIU-P flight mate, mate to EGSE install SIU-P     0 12
  P0     EPU-P0 flight mate install EPU-P0     0 12
    R   EPU-R flight mate install EPU-R     0 12
Totals 418 180
* not in critical path