16 Tower w/ACD Test Plan (pre-FSW)
Rev. 11/8/05 L.Wai
Sub-Series Test Purpose Time (hr) Totals Time (hr)
ACD Integ. safe-to-mate LAT interface safe-to-mate 8 ACD Integ.: 8
LAT CPT AEM/ACD Clock Phase Bit Test ACD/DAQ clock 4
LAT CPT GASU register test Check for GASU errors 4
LAT CPT register test - redundant GASU/PDU Check for TEM errors 4
LAT CPT register test - primary GASU/PDU Check for TEM errors 4
LAT CPT ACD CPT Baseline LAT CPT 16
LAT CPT LAT CPT - TKR Section* Baseline LAT CPT 2
LAT CPT LAT CPT - CAL Section* Baseline LAT CPT 2 LAT CPT: 36
Trigger ACD Channel Uniformity Check ROI and CNO arrival times with CI 4
Trigger ACD Hitmap Latching Optimize hitmap latch delay and stretch 4
Trigger ACD CI Circuit Retriggering** Verify ACD CI circuit behavior (NCR706) 0
Trigger CAL Channel Uniformity CAL-LO and CAL-HI arrival times with CI 2
Trigger CAL FLE Muon Scan FLE threshold and trigger mask for timing 6
Trigger ACD TREQ with ext trigger** ACD ROI arrival times w/ muon tel. trig. 0
Trigger ACD Trigger Rate Test Optimize ROI trig. for CAL/TKR TREQ test 8
Trigger CAL, TKR TREQ Alignment CAL-LO, TKR arrival times w/ ROI trig. 8
Trigger ACD TREQ with TKR trigger ACD ROI arrival times w/ TKR trig. 8
Trigger ACD, CAL, TKR TACK Scan Optimize TACK for all three subsystems 8
Trigger Trigger Efficiency*** Trig eff. study for all three subsystems 0
Trigger ACD Veto Mode Run*** Cosmics run w/ CAL-LO || (TKR && !ROI) 0 TRIGGER: 48
CALIB CalibDac (CAL discriminator scans) CAL thresholds calibration 5
CALIB CalibGen (CAL charge injection scan) CAL ADC calibration 3
CALIB MuTrig  (CAL muon data)**** CAL energy calibration 2
CALIB TE601 (TKR threshold scan) TKR threshold calibration 4
CALIB TE602 (TKR full range charge inj. scan) TKR TOT calibration 4
CALIB TE604 (TKR charge scan at threshold) TKR threshold dispersion 4 CALIB: 22
TKR perf. TE702 (TKR trigger jitter) tracker performance test 4 TKR Perf: 4
SVAC e2e B-2, B-10, B-13 (1 minute ea.) Configuration Validation 2
SVAC e2e B-13 (15 min) SVAC data collection 2
SVAC e2e B-10 (15 hours) SVAC data collection 20
SVAC e2e B-2 (4 hours) SVAC data collection 6 SVAC: 30
* data analysis may be deferred TOTAL: 148
** these tests may be deferred
*** these tests may be replaced by equivalent SVAC phase 2 runs
**** this test may be reduced in scope
Sign-off: I&T Management _____________________
Systems Engineering _____________________
Quality Assurance _____________________