GLAST Integration and Test Header

LAT I&T TRR Phase 0

Location: GLAST III conference room (SLAC Building 234)
Call in number:   510-665-5437    ID:  4762

Date: November 3rd, 2005

Agenda/Presentations:
03:00-03:30 PM  -  LAT Test Phase Overview (K. Fouts) [PDF] [PPT]
      - I&T Plan/Schedule
03:30-05:00 PM  - Integration Readiness (K. Fouts) [PDF] [PPT]
     - Requirements

     - Mech. Procedures

     - MGSE
     - ACD Installation
     - Risks
     - Hardware Status

     - Summary

Date: November 4th, 2005

Agenda/Presentations:
08:00-08:30 AM  -  I&T Plan Review (K. Fouts) [PDF] [PPT]
08:30-09:00 PM  -  System Test Definition Plan/Schedule  (P. Hascall) [PDF] [PPT]
09:00-10:00 AM  -  Electrical Test Readiness -   
      - Test Status and Plans                                 (L. Wai) [PDF] [PPT]
      - Test procedures and EGSE configuration     (B. Grist) [PDF] [PPT]
      - Test Software (LATTE) Status                   (R. Claus) [PDF] [PPT]
10:00-10:30 AM  -  NCR Review  (P. Hascall) [PDF] [PPT]
 