Notes on the Engineering Model - 03/27/01
Martin Nordby is working under the assumption that
the Engineering Model has
- 3 instrumented silicon trays (TBR)
- fully instrumented calorimeter ( is the final
electronics there ?)
- 1 (TBR) ACD tile (at some point we will have a
full ACD mechanical model)
For the moment (after talking to R. Johnson) there
are 2 possible approaches for the tracker mainly driven by schedule
- EM has no instrumented trays and is used for
mechanical/environmental test only.
- EM has 3 trays (not sure how many with thin or
thick converter)
BEAM TEST
- Hard to justify unless we have the
appropriate beam already in 2002 (very unlikely). The EM itself does not
teach us more than what we have learned from previous SLAC test beams.
- Could drive the DAQ development ? Not really.
In principle one could study DAQ issues by using cosmic rays or software
enabled triggers.
- If we come up with a well defined roadmap for
the electron rejection using the TOT, then we could justify some studies on
the electron background rejection using the new tracker electronics (very
weak rationale for a huge test beam enterprise)
- Calorimeter is fully instrumented, but to do a
"CAL only" test beam, the SLAC beam may not be appropriate. Then
one can consider an EM test at CERN/GSI/FNAL. In this case, since the
calorimeter would be the driver, that has to fit their schedule too.
- ACD does not have enough instrumentation to
justify a test beam request.
- Most of the DAQ functions can
be tested without the beam: command/control, setup, housekeeping, error
reporting/correction, ... The abilities of the system can also be exercised
by generating triggers at high rates by turning down the thresholds and/or
charge injection and/or pulse generators. All that has to happen long in
advance of the beam test! (Steve Ritz)
- Use EM to characterize the
future beam for calibration.
COSMIC RAYS
- EM certainly should be tested under cosmic rays
since it will help setting up test instrumentation system at SLAC and one
could study some DAQ issues.
- We will gather a valuable amount on
environmental data that could be used to understand our requirements on the
internal alignment of the tracker.
SOFTWARE
- Tracy Usher seems to believe that by early June
we should have a MC available with enough flexibility that one could try
different tray configurations for the EM. OF course, we need to convince
ourselves that it is worth the effort.
SCHEDULE
- Put EM in the beam test to tune the beam. If
schedule permits then add 1 or 2 towers and then 4 towers ? (Hartmut)
EQUIPMENT
- Need to investigate Vavra's telescope for
cosmic muons