Darren,
 
The key milestones to get this program back on track are:
 
1. Verification that the water blast process indeed resolves the separation problem. The action items are:

2. Receive 75 ohm resistors from SLAC or instructions to continue building with 100 ohm resistors. Assume receipt by 12/17/04
 
3. Parlex to receive punch and die for adhesive preform                                               12/15/04
 
4.
Parlex to determine proper preform size.                                                                 12/17/04
 
5.
Parlex to begin assembly of completed composites currently at assembly                 12/17/04
    Estimated assembly rate of 8 units per week
 
Frank