LAT ASSEMBLY AND INSPECTION DATA Record #631
LAT Assembly Information:
Equipment Title
Drawing No.
Rev
Serial No.
Tracker Tower A Receiving, Handling & Acceptance Top Level Procedure
LAT-PS-05471
Reference Designator
Subsystem
Equipment Class
Prepared by
Tracker
Flight
Steve Lundgren
Approvers:
Responsible Engineer
Manufacturing Engineer
Quality Engineer
D. Rich
B. Estey
J. Cullinan
Date Signed:
Date Signed:
Date Signed:
Step Instructions:
Step#
Step Instruction
OperatorID
OperatorDate
OperatorStamp
Update Record
10
The purpose of this AIDS is to receive in Tracker Tower and perform the following tests, approve & accept the Tracker prior to hand-off to I&T
1/12/2005 10:33:55 AM
20
Perform Tracker Receiving and Post-Shipment Handling Procedure LAT-PS-05471-02. Engineering Review & Approval of test data
1/24/2005 2:10:42 PM
25
Record Tracker Tower Serial Number here:_____________
30
Perform Post-Shipment Electrical Tests per LAT-PS-05481-01. Engineering review & approvel of test data.
1/24/2005 2:10:56 PM
35
Perform Tracker Tower Alignment Verification. Use LAT-DS-04660-01 & INFN programs to measure Tower points. Engineering review & approval of measurement data.
1/14/2005 8:59:17 AM
40
Install EMI Shield and Taping per LAT-PS-05442-01, Tracker Tower Shielding Plan.
1/14/2005 9:24:47 AM
45
Perform EMI Acceptance Testing per LAT-TD-05462-01. Engineering review & approval of test data.
1/24/2005 2:11:24 PM
50
Perform Hand-off Electrical Test per LAT-PS-05481-01. Engineering review & approval of test data.
1/24/2005 2:11:46 PM
60
Hold I&T Hand-off Meeting. Engineering & LAT QA review & approval of complete data package
1/12/2005 10:39:21 AM
70
Close out this AIDS tower has been handed-off to I&T. Retain this AIDS with all supporting documents such as Data Sheets, etc. in the B33 QA Records Retention File.
1/14/2005 9:06:25 AM