Minutes of the 4/15/04
Tracker staff meeting
Notes from Jim Martin
Attendees: Rich, Menning, Martin, Tice, Scholz, Nordby,
Brez, Bagagli, Menon, Rapposelli, Venator
ACTION ITEMS (Dave - please reword if needed, and assign
to people)
1. Tell Sandro if Tom Borden has received full set of EM sidewall
coupons
2. Send new PS number to Sandro/Riccardo for BT/TT Assembly
procedures (Done by Robert: LAT-PS-03613)
3. Plyform to provide Travelers and database for PRRs
4. Sandro to send email to Martin Nordby describing exactly what has
been laminated RE facesheets for BT/TT
5. Sandro/Riccardo to give Martin feedback Monday on TT closeout
drawings
6. Nanda to fill in the Matrix to best of his knowledge and send it
to Dave Rich et al
7. Review DTP List together:
Tackle TT/BT and sidewalls Monday morning, someone must arrange the
telecon
8. Jim M to get the spec to which the prepreg was ordered and get it
into LATDocs - Sandro will send the spec to Jim M from INFN
9. Dave: is there an action
item for the Ti washers?
10. Riccardo:
Riccardo to send recommendation on how to change inserts for simplifying
tooling.
11. Riccardo to ___?__ RE critical dimensions
for reviewing __?__
12. Riccardo to send redlines for Midtrays
13. Martin and Joe to review inspection data on
BT closeouts, and Jeff will oversee packaging and shipping ASAP
14. Someone to look at whether Dave can
hand-carry the Ti flexures to INFN.
Sandro asks: has Tom Borden received full set of EM
sidewall coupons? Dave will check
Dave introduces PRR/TRR
Matrix for tracking closure on input items to the PRRs and TRRs that are coming
up - Robert asked for this, and names of responsible people for each item.
PRR for BT and TT, 27
April: Sandro/Riccardo
Sandro says: they need a PS number for the Assembly
procedures
Travelers: would be provided by Plyform - may not be
quite ready, but PRR team should establish a plan for completion
Materials: face sheets for BT and TT have been
laminated to existing drawings - Martin very concerned - see ACTION ITEM below
INFN: responsible for Tooling and fixture
OTHER PRRs, TRRs: see ACTION ITEM below
Tom V concerned that we need
to go through the Drawing Tree and Parts List as a group - he suggested Friday
morning, but Monday morning (PDT) is the first time Riccardo will be available.
PO for sidewall prepreg has
been released from Plyform to COI - to what specification? see ACTION ITEM below
Titanium washers: do new ones need to be made? Design is not finished, John Ku has work
still to do. Schedule pressure is a
driving factor: fab is 4 weeks,
according to Jeff, and design completion would take a week. Need date is 1 June. The change must be compatible with the
tooling - Martin would need to see the tooling drawings. Tom V worried: we should not change anything that we don't need to change. Some discussion between Martin and Sandro on
details. Dave: if Sandro can verify that thickness change
would not affect tooling, we would build Tower A with existing washers if
schedule requires, but we would switch over to the new washers at Tower B or
1. Sandro worry: increases confusion.
TT closeouts: Martin needs feedback now on the check
prints. See ACTION ITEM below. Some detailed technical discussion between
Martin and Sandro.
BT: Tooling and pins still have to me made. Riccardo will send recommendation on how to
change inserts for simplifying tooling.
See ACTION ITEM below.
Critical dimensions for
reviewing: Riccardo and Sandro to
follow up.
Redlines for mid-tray
drawings: Riccardo wants all the
assembly drawings and then can do the check.
BT closeouts: See ACTION ITEM above.
Other action items from last
week were completed.
Reminder about Robert Ruland
being at Pisa on Thursday/Friday, April 29/30.
Discussion of new CMM and software for same at INFN, which enables
comparison to a solid model - can review this capability then.
Titanium flexures: we expect the first parts to be shipped to
SLAC Tuesday, April 20th, then 7-10 calendar days to get to INFN unless we
hand-carry it.
MCMs: production was stopped because of alignment
problems; it is about to be re-started.
77 short MCMs and 11 talls were started into production prior to the
halt. The first 5-10 are still on
schedule for April 22 delivery. They
need to be burned-in, and they need to be at INFN end of first week of
May. This is **critical path** for
G&A.
Conical washers and
clamps: Nanda wants to talk about the
latest ideas through; latest concept looks difficult to use. Mike M:
concept only at this point, quite a few drawings to do yet, not having
cones in hand makes it harder.
Nanda: Emilio can put together
ideas and send them to Mike.