Minutes of the Tracker
Technical Meeting
December 11, 2003
Agenda:
- Discussion and decision on going forward with proposed
flexure/Grid interface
- Discussion on pros and cons of reworking the EM tower into
the flight interface configuration
- Update on T/V test planning.
- Discussion of need to investigate possibilities for TEM
temperature control during flight T/V testing
- Startup of tray panel assembly, non-flight and flight
- NCR on honeycomb
- Open action items
- A.O.B.
Action Items
1.
Jim,
Darren: disposition the honeycomb cores
2.
Jeff:
find a delivery schedule for new cores
3.
Sandro:
send samples of defective cores to SLAC
4.
Tom
Borden: find the thermal conductivity number used by Jeff Wang and send it to
Tom McCarthy.
5.
Sandro:
ship the drill fixture (on its protective plate) to SLAC asap
6.
Tom/Robert/Jim:
make a more detailed schedule for getting to the next vibration test
7.
Jeff:
track down the missing Hysol glue and send the invoice to Sandro
8.
Sandro:
check with Alenia on availability for vibration testing starting January 26
9.
Tom:
put together a test plan for the new concept and send it to Sandro
10.Sandro: send to Tom
information on the number of inserts needed for completing the sidewall test
coupons
We considered Sandro’s idea
about machining the corner bracket and flexure in one piece. Erik doesn't think it is possible unless the
height of the tower is raised several millimeters. Otherwise the EDM wire used to cut the flexure blades will cut
into the corner bracket. Tom said that BJ
is preparing an assembly drawing for flexure and bracket. The plan is that the machine shop will be
responsible for delivering a matched pair already assembled.
Nanda reported on the
thermal-vacuum test meetings. They
discovered that there had been no parasitic analysis done in the test
configuration. Doing some analysis
showed a high loss of heat through the thermal blanked compared to dissipation
down the tower. We will have to modify
the test setup to include an aluminum cage around the tower with its aluminum
sides heated. Also, they plan to keep
the TEM box decoupled from the baseplate and controlled to approximately room
temperature. They are making progress
on defining actions. Jack has a list,
including responsible parties and due dates.
They are working toward a TRR in the first week of February, with the
test following in 10 days. Tomorrow
they will go to Rome and will meet with Alenia Monday.
Sandro has sent honeycomb NCR
data (now posted on the Tracker web site in http://www-glast.slac.stanford.edu/Tracker-Hardware/QA/NCRs.html). The problems are of several types: Extra
walls, cuts not parallel to cell rows, dual colors, and crushing damage to
cells near the periphery. Heavy cores show
only the problem with non-parallel cuts.
For light cores, however, only about 5% are perfect. SLAC will consider the data and arrive at a
disposition. Robert said that schedule
demands that we try to find enough good cores for the first flight tower. Sandro reminded us that he must return all
cores one way or another to the USA, for customs reasons.
Jeff will find a schedule
for delivery of new honeycomb.
Sandro will send samples of
the damaged honeycomb tomorrow.
Sandro said that even though
the heavy bottom tray honeycombs are mostly good, we still are short of them. Not enough spare top tray honeycombs were
ordered the first time, either.
Tom McCarthy said that he
would like to know the number Jeff Wang is using for thermal conductivity of
the sidewall material in his model.
Robert commented that we also need to measure that number from Plyform
coupons.
Regarding the flexure-Grid
interface, Tom said that Mike Foss will complete detailed drawings today of the
concept being worked at SLAC (see http://www-glast.slac.stanford.edu/Tracker-Hardware/ART/vibe/vibe.html). Then Tom will look at modifications
necessary to the vibe fixture and existing flexures.
Sandro said that there are
serious issues with removing the bottom tray.
He asked if the conical section could not be put into the outer part of
the flexure, as an insert into the existing counterbore. Tom said no, that since the load of the
tower bears on the conical section, it has to extend all the way to the
Grid. Otherwise there will be a large
bending moment on the bolt.
Robert asked if we couldn’t test
the new concept with the 2nd bottom tray.
To make that possible, Pisa will send the drilling tool to SLAC
immediately. Tom cautioned that it’s
high precision is fragile, so it must be fixed to its aluminum base plate for
shipping.
Robert asked if the epoxy in
the side-flexure liquid bushing can be removed after removing the bolt. Tom said yes, that this will have to be done
after dismounting a tower from the vibration fixture and before putting it into
the Grid (the same bushing cannot be used, because the fixture and Grid
alignment won’t be the same). Tom said
that the conical bushing has a self-extraction feature to make sure we can get
the thing apart.
Sandro cautioned that a realistic
schedule needs to be made for the vibration test. He estimated at best 1 week to dismount, drill, and remount the
tower. More if there is any
problem. His biggest concern is the
cables. Two spares are in Pisa, but 6
cables have no spares. Tom will take
parts there to remake at least 1 cable if necessary. There are not enough Nanonics connectors available to make
another complete set of those cables.
Jeff said that he sent the
Hysol adhesive for potting connector pins.
Pisa has not seen it. Jeff will
track it down and will also send the invoice to Sandro.
Tom estimates this for a
schedule: test the tooling the first week of January and then go to Italy the
following week. Go into the vibration
test at Alenia the week of January 26? Sandro
will check this with Alenia.
Erik said that they could modify
the static test fixture to accommodate the new flexure-grid interface design. Tom said that it would be useful to use it
to study hysteresis in the new design (should be much smaller than in the old
design). In any case, the static test
fixture will be needed for the flight towers.
Sandro asked Tom to send a
test plan to Pisa for checking out the new interface design.
Sandro will send information
tomorrow on the inserts needed for the sidewall test coupons, so Luca can carry
them back with him on Saturday. In early
January they will send coupons with inserts for testing at COI. Plyform will make a complete new set of
coupons for testing tensile, compression, and shear. None of the coupons will be taken from the panel edge this time. They will test them in early January, to be
completed before the vibration test.