Minutes of the Tracker
Technical Meeting
January 23, 2003
Action Items:
1.
Tom:
email the pro-forma invoice to Sandro for the MCMs.
2.
Tom:
call Teledyne to check on the EM MCM status.
3.
Robert:
get SLAC to assemble two cables for Pisa use.
4.
BJ/Nelson:
revise the bias circuit design.
5.
Tom:
get the tower assembly fixture design moving.
6.
Tom:
send the schedule to Sandro to mark up.
7.
BJ:
update the closeout drawings with new pin hole
8.
Tom:
fix the assembly tooling page in Cyberdocs.
9.
Robert:
update the Bari EM test plan in Cyberdocs.
Robert reported that 6 MCMs
shipped out yesterday from SLAC. They
should arrive no later than Monday.
Sandro asked Tom to email the pro-forma invoice.
Luca mentioned a problem
seen in testing the MCM in Pisa. One
channel appears dead when strobing all channels but reappear when strobing
fewer channels. The funny channel is
1208.
Tom gave the status of the
dummy MCMs for the mechanical/thermal tower.
19 were shipped to Italy.
Teledyne is starting now to finish the rest. They already have pitch adapters installed. Tom will call Teledyne to check on the
status.
There was a discussion of
cables. We need to get the cables from
Parlex still for the mechanical/thermal tower.
Robert wants to assemble two cables at SLAC for Pisa use.
SAndro reported that they
have the 4 trays for the mini-tower.
They measured the parallelism of their surfaces. The results are good. These cannot go into vacuum because of
insulation added for shielding the ground plane.
Sandro said that we need a
design change for the bias circuit. We
must hold the shield plane back from the cut edge by a few mm, to avoid danger
of cutting into the plane.
The tray for thermal-vaccuum
testing will use a Kapton foil assembled with an insulating plane at CERN under
vacuum.
Plyform is continuing the
work on the EM tower trays.
G&A is ready to work on
trays. Sandro hopes by next Tuesday to
have one layer of ladders bonded to an MCM.
Sandro asked about the
status of the tower assembly fixture.
Ossie is on disability now but is working on the design from home. Tom will work this issue quickly. It needs to be shipped to Italy in March.
Sandro said that Pisa cannot
spend sidewall money now in Italy. He
suggested in exchange to fabricate the tower-assembly tooling. Tom said that SSDs could be ordered in 3 or
4 months as a trade. Sandro said that
Italy won't have money for that until July.
G&A is continuing with
encapsulation of flight ladders. They
plan to test again after the first 40 ladders are done. Sandro said that they need inox boxes from
G&A for MIPOT to use, but that is delayed.
The week after next Sandro will go to MIPOT. All parts and materials will be available at MIPOT at the
beginning of February. MIPOT will do 10
ladders first, then review.
Tom talked about the tray
production schedule. He figures that we
need 13 working days at Plyform for 2 towers of trays. He put this plus the vibration test into
schedule as 13 days. Tom will pdf this
and send it to Sandro to mark up. The
schedule shows a start in March.
Closeout material is in hand.
More is arriving next week. For
honeycomb Tom is working on a quote from Plascore. Sandro said that they need to modify the tooling to distinguish
between front and back. We need BJ to
put these changes into the closeout drawings.
Sandro said that the assembly tooling is not visible in Cyberdocs. Tom will fix that.
The schedule indicates that
the tray PRR needs to be held in early March.
Tom would like to go to Italy the week of Feb 4 and spend time at
Plyform working on process documentation.
This is too early for Sandro.
There was a discussion of EM
testing. We plan to vibration test and
thermal test the trays to qualification levels. Robert needs to update Cyberdocs with the latest Bari plan.
Sandro said that the 5th
working tray, destined for thermal-vac testing, he will use encapsulated
ladders from the flight build (i.e. with the new encapsulation material).
There was a short discussion
of the bottom tray. Hytec is proposing to reinforce the closeouts wit M55J
fabric on the inside, in order to have enough margin. We also need some relief in terms of notching at the
resonance. Otherwise the tower will see
45g accelerations according to the model.
Martin will set up a telecon with GSFC to discuss this issue.