Tracker Status
July 23, 2004
Tower-A Tray Panels
-
Production is getting back on track following the problems with
Kapton adhesion to the tungsten. The tungsten foils have been
bead blasted with a 1-micron roughness, and
plans are being
finalized to prepare the Kapton surface
also.
- Plyform
has committed to a schedule for the Tower-A trays and
will work Saturdays through August 6 to
complete the work by
that date on all Tower-A trays plus some
spares.
- The TRR
for the Tower-A bottom tray static test was completed this week.
MCMs
- 222 MCMs
have been produced, and 194 have been received by SLAC
- 109 of
them have been reworked with 75-ohm resistors for the clock
bus terminations. The rework is proceding rapidly, and finally
SLAC purchasing authorized a PO change for
Teledyne to start putting
the 75-ohm resistors on in production.
- Only 2
flight trays will have MCMs with 100-ohm termination, as a
stock of reworked MCMs is now in Italy.
- Some of
the revised pitch adapters finally arrived, and now there will
be a push to qualify them in the process and
get more ordered.
Tray Assembly (MCM and ladder integration)
- 2 flight
trays have trailblazed the entire process through MCM mounting,
ladder mounting, wire bonding, and
encapsulation with excellent results
so far.
- G&A
did a beautiful job of developing the MCM attachment, wire bonding,
and encapsulation processesover the past few
months, and on these trays
the number of bad channels (out of >6000),
measured before encapsulation,
could be counted on one hand and was far
below the maximum allowed. Only
2 channels were missing the wire-bond
connection. The cause was found to
be contamination on the pitch adapter
circuit. Those bonds were reworked
and a new, more aggressive cleaning of the
pitch adapter will be done
in the future.
- Early
next week the encapsulated trays will be functionally tested and
then put through thermal vacuum cycles as
final qualification of the
process.
- G&A
has agreed to defer vacations until the Tower A trays all are
assembled.
We expect that the last tray will be done and ready for
testing around August 8.
Sidewall Assembly,
- Plyform
will have the Tower-A sidewalls completed before the August
vacation shutdown.
- SLAC is
preparing the PO for the remaining prepreg needed for the
flight towers.
Flex-Circuit Cables
- Coupons
from the first cables were sent to NASA for testing.
- Parlex
agreed upon a new delivery schedule for the remaining flight
cables which supports the Tracker schedule.
Heat straps
- The first
sets of heat straps are in Italy ready for their incoming
inspection.
The tie-down bars need to be modified by cutting them
from 1 piece to 2, to facilitate
installation (the drawings have
been so modified).
Interface Hardware
- The
Tower-A hardware will be shipped to Italy next week. There was
a delay with the hex bushing, which was
originally made from the
wrong material and had to be redone. The delay had no impact on
Tower A, however.
Cable Corner Brackets
- The
design was signed off this week, and procurement has begun. These
are the last pieces of Tracker flight
hardware to be designed.
Tower Fasteners:
- The M2.5
100-degree head screws were inspected and are good to go.
- The 2mm
pins are also inspected and ready.
Tower Assembly
- The
detailed procedure documents and assembly drawings are still in work.
- The
CMM-based alignment procedure was successfully developed and tested.
The cones can be readily adjusted to better
than the needed precision.
- Assembly
of Tower-A is scheduled for the last week of August.
Environmental Test
- INFN
located a TQCM to be used at least for Tower A testing.
- The
environmental tests for Tower A should be done in the time frame of
September 6 through September 17.
MGSE
- The cable
holding plate was completed.
- The
lifting fixture was proof loaded and is ready to ship.
- The inner
shipping container was assembled and will be proof loaded
next week.
- The
cactus-arm cable bending tool is in the shop.
- The
tooling-ball nests are in the shop.
- 18 vibe
fixtures are still in fabrication.
- The outer
shipping container has been spec'ed out and a print is
in preparation for review. An environmental recorder with battery
and memory sufficient for the entire trip to
SLAC was found and is
being procured.