Tracker Status
June 11, 2004
Tracker-Grid Interface
- Flight
cones, studs, shims, and hex bushings are on order from AMT.
-
Nitronic-60 nuts are on order from Diamond Tool and Die.
- Work is
in progress on the remaining GSE tools for installation.
Bottom/Top Tray Panels
- The
assembly drawings are completed and released.
- The new
EM bottom tray was assembled this week and is being
dimensionally checked by CMM today.
- The
static test will be executed on the EM bottom tray this weekend.
- Top tray
closeouts are ready to be machined.
- The
Tower-A bottom tray will be assembled next week.
Mid Tray Panels
- 17 trays
have been completed through ESPI testing, and
7 trays are completed up through vibration
testing.
MCMs
- 85 MCMs
were completed at Teledyne as of a week ago.
- We expect
that 99 will have been completed by COB today.
- Steps are
being taken to get the rate back up to 5/day next week.
- An MRB is
being held on Monday to decide whether to rework the
MCMs with 75-ohm termination resistors on
the clock busses.
Tray Assembly (MCM and ladder integration)
- Assembly
drawings are ready to go out for sign-off.
- The
procedure document is out for review.
- The
outcome of work at G&A this week is that the MCM mounting tooling
needs another tweak. Tray assembly should start next week, and we
will investigate with G&A how to make up
the schedule slip.
Sidewalls
- Prepreg
is at Plyform.
- There
have been some problems with procuring the desired aluminum foil,
so we are looking at a possible change in
spec to use a foil quickly
available in Italy.
- The
release of the assembly specification document is still in iterations.
Flex-Circuit Cables
- The
flight cables are on order, with 2 sets due July 8.
Tower Assembly and Alignment
- Work is
moving forward to develop and test the alignment procedure using
at SLAC the I&T mockup tower.
- After the
EM vibration test, that tower (with its flight-like bottom
tray) will be used to test the procedures in
Pisa.
Vibration Test
- The
vibration fixture should be done in the SLAC shop today.
- The studs
were coated and Monday/Tuesday will be fitted with
locking devices.
- Plans are
in work to hand carry these items to Pisa mid next week.
- TRR end
of next week.
- We are shooting to start the vibe test June 21.