Tracker Status
June 25, 2004
EM Vibration Test
- The test
setup began Monday at Alenia and all test cases in z, y,
and x were completed by COB Thursday, one
day early.
- All
preliminary results point to a completely successful test. The
frequency shifts after-vs-before random vibe
were at most 1%. The
resonant frequencies and Q's were consistent
with expectations.
No fasteners were observed to lose torque,
and no damage was observed.
Tower-A Mid Tray Panels
- During
thermal-vacuum testing of tray panels (no electronics or silicon),
debonding of bias circuits was observed on
the tungsten side of the trays.
This is introducing a delay to review and
improve the tungsten surface
preparation prior to bonding of the Kapton
circuits.
MCMs
- Quote for
MCM resistor rework (75 ohms) are due today from Teledyne
and Zentek.
- 36 MCMs
are in burn-in at SLAC.
- Parlex is
ready to start producing prototype improved pitch adapters as
soon as SLAC releases a PO to them.
Tray Assembly (MCM and ladder integration)
- G&A
has successfully completed wire bonding tests on preproduction MCMs.
- The
bonding procedure for MCMs has been finalized.
- They are
working on finalizing the process and tests for wire bond
encapsulation.
- Assembly
of 2 non-flight trays should begin early next week.
Flex-Circuit Cables
- 6 C0
cables were received at SLAC and tested.
Two of them have problems
that are under investigation.