Tracker Status
May 14, 2004
Tracker-Grid Interface
- Testing
is in progress on evaluation hardware by pull testing.
- 34
cone-stud hardware sets are scheduled to arrive next week.
- Design
work is in progress on tools for cone extraction, adjustment,
and alignment.
Bottom/Top Tray Panels
- The
design details are completed and signed off.
- Insert
machining started this week but was then halted when it was
discovered that the vendor shipped the wrong
alloy. A decision was
made to use titanium. Inserts will be ready May 28.
- Machining
of the assembly tooling is still in progress but should be
done next week.
- Closeouts
and titanium parts are in Italy.
- Aluminum
core for the bottom tray is on order, but existing cores can
be readily cut to size for the first towers.
Mid Tray Panels
- 15 (9
light, 6 heavy) produced through ESPI and GND testing.
- These
were dimensionally checked and 2 rejected.
- 4 were
completed through bias circuit bonding and passed vibration
testing at Centrotecnica.
Ladders
- Less than
1000 of the full order of 11,400 SSDs remain to be tested.
- 1055 ladders assembled, with 16
rejected.
MCMs
- Total of
21 received, including 12 this week.
- 11 more
have been shipped from Teledyne, and 7 should ship today,
giving a total sufficient for Tower A.
- 6
completed thermal cycles and burn-in and passed final test, but
were locked up by QA for procedural
nonconformance.
- The
burn-in system with EM-2 TEM/PS was acceptance tested according
a newly released procedure this week.
- 12
completed thermal cycles and are starting burn-in.
Tray Assembly
- G&A
is completing tests of the new tooling and procedures for MCM
mounting.
- MCM mounting
pin design was completed and is out for release. These
objects need to be machined and plated
before tray assembly can
begin.
- Work is
in progress on updating the relevant assembly drawings.
- The
procedure document is out for review.
Sidewalls
- Prepreg
for the first couple of towers should be delivered next week.
- The
fabrication specification document is out for release.
- Drawings
have been released.
- Titanium
washers are being procured.
Flex-Circuit Cables
- The
designs are complete and reviewed and final redlines are being
incorporated.
- A final
check of mechanical vs electrical designs will be done and
the drawings sent out for release next week.
Tower Assembly and Alignment
- A
conceptual design was completed for an aluminum part to go on
the top of the tower to fasten the cable
ends and also support
the alignment retroreflectors.
- We
determined that the tower mockup being assembled by AI&T can
and will be used to debug and prove the
alignment software and
procedure.
GSE
- The
lifting fixture design is still in progress but converging.
- The
vibration fixture drawing is out for release.
- The cable
restraining plate is under design.
- Cable bending tools are being designed.