Tracker Status
May 21, 2004
Tracker-Grid Interface
- Some
progress was made on understanding torque during static
testing.
- 34
cone-stud hardware sets are delayed until next week.
- Good
progress is being made on the GSE.
Bottom/Top Tray Panels
- Top tray
assembly drawings went out for release.
A few details
need closure on the bottom tray assembly.
- Assembly
tooling is machined and was checked dimensionally this
week.
- The
static test fixture plate was received at SLAC and inspected.
- Titatium
for inserts should be in hand by today, and machining will
be done next week.
Mid Tray Panels
- 3 more
panels were vibration tested with excellent results.
- The T/V
procedure for panels is out for release and the setup is
ready to go at Roma-II.
- Work is
in progress to peel test the black paint to resolve an NCR.
MCMs
- Well more
than enough for Tower A are at SLAC.
-
Production and test is going smoothly now at Teledyne. The incidence
of ASIC failure on MCMs at MIP-2 testing is
zero for the past couple
of weeks, after visual inspection of all the
die.
- 15 MCMs
will complete burn-in tomorrow, then final test. At least 11
of them should ship on Monday to Pisa (4
have an open NCR but are
probably okay---TBD).
- NASA QA
reviewed Teledyne operations yesterday.
Tray Assembly
- G&A
should complete next week tests of the new tooling and
procedures for MCM mounting.
- Material
should be available today for machining the TMCM pins.
- Work is
in progress at SLAC on updating the relevant assembly drawings.
- The
procedure document is still in work.
Sidewalls
- Prepreg
for the first couple of towers is in transit.
- The
fabrication specification document is out for release.
- Drawings
have been released.
- Titanium
washers are being procured and should arrive May 25.
Flex-Circuit Cables
- Finally
the drawings are out for release.
Tower Assembly and Alignment
- A
conceptual design was completed for an aluminum part to go on
the top of the tower to fasten the cable
ends and also support
the alignment retroreflectors.
- We
determined that the tower mockup being assembled by AI&T can
and will be used to debug and prove the
alignment software and
procedure.
Vibration Test
- The
vibration fixture drawing is released and procurement in
progress.