Tracker Status
Tray Assembly
- A Tracker response to the ART report was drafted and submitted to the project office as a plan forward to resumption of tray fabrication.
- GSFC completed etching and priming of at least 100 tiles.
- INFN met with Plyform to start implementation of the recovery plans. Plyform’s response has been very positive thus far.
- Wire and compression pad materials were found for testing of the ART recommendations.
MCMs
- Production and testing is continuing at Teledyne, with 52 in the production line, including 14 in source inspection.
- Burn-in and final testing is progressing at SLAC, with 36 MCMs presently in the thermal chamber.
- Work in progress on several fronts at SLAC to keep materials flowing into the production line.
- Work progressed on how to address the conformal coating workmanship issues, and investigations into the short circuits continued.
Flex Circuit Cables
- More meetings were held on the coupon testing issues.
-
Some trial cable installations were carried out in
Misc. SLAC Deliveries to INFN
-
The
-
Epoxy, tape, and 68 bias circuits were shipped to
- The first corner brackets that go at the top of the tower for mounting cables were badly manufactured and are non-flight but will be used for a trial assembly. The manufacturing errors are being corrected.
Tower Assembly
- The trial assembly of a tower will start next week, and all tests and measurements should be completed after 2 weeks. Several non-flight trays were reworked, with MCMs installed, so that the resulting tower will be functional and will provide a platform for verification of the functional tests as well as alignment and mechanical tolerance measurements.