Level 3
SAS L3 Requirements Review | 4/20/2001 | 4/20/2001 |
SAS PDR | 8/17/2001 | 8/17/2001 |
CAL prototype calibration alg | 5/15/2002 | |
ACD calibration algorithm | 6/21/2002 | |
TKR Dead/Noisy Strips alg | 6/21/2002 | |
SAS CDR | 9/4/2002 | |
TKR Tower and Tray Align alg | 1/22/2003 |
Level 4
Prototype Release Manager in Place | 3/11/2002 | |
AV: 1st Major Release of Simulation & Reconstr'n | 4/09/2002 | |
Second Major Code Release | 10/25/2002 | |
Annual Evaluation & Tracking of LAT Performance | 12/23/2002 | |
Photon Database Technology Implemented | 1/14/2003 | |
Completed Instrument Response function | 5/29/2003 | |
Annual Evaluation & Tracking of LAT Performance | 8/29/2003 | |
Production Version of Data Processing Facility | 1/08/2004 | |
Annual Evaluation & Tracking of LAT Performance | 8/31/2004 | |
Annual Evaluation & Tracking of LAT Performance | 8/31/2005 | |
Science Tools in Place | 11/21/2005 | |
Final End-to-End test | 1/04/2006 | |
Data Processing Facility Completed | 1/04/2006 |