Document # |
Date Effective |
|
LAT-TD-## |
|
|
Prepared by(s) |
Supersedes |
|
L. Latronico |
|
|
GLAST LAT Technical
Note |
|
|
Subsystem/Office |
||
Tracker Subsystem |
||
Document Title |
||
Gamma-ray Large Area Space Telescope (GLAST)
Large Area Telescope (LAT)
Tracker Subsystem
End Item Data Package
Tower 16
DOCUMENT APPROVAL
Prepared
by: |
|
|
|
|
|
L. Latronico |
|
Date |
Approved by: |
|
|
|
|
|
E. Rapposelli |
|
Date |
|
|
|
L. Latronico |
|
Date |
|
|
|
N. Mazziotta TKR Subsystem Environmental Test Lead Engineer |
|
Date |
|
|
|
A. Troianiello |
|
Date |
|
|
|
Robert P. Johnson |
|
Date |
|
|
|
A. Brez |
|
Date |
LAT Acceptance
|
|
|
Dick Horn |
|
Date |
|
|
|
Pat Hascall |
|
Date |
|
|
|
Elliott Bloom |
|
Date |
|
|
|
Darren Marsh |
|
Date |
|
|
|
Other |
|
Date |
CHANGE HISTORY LOG
Revision |
Effective Date |
Description of
Changes |
01 |
|
Initial Draft |
|
|
|
|
|
|
|
|
|
|
|
|
The purpose of this document is to collect all the data for the Glast LAT Tracker (TKR) Tower End Item Data Package (EIDP), in compliance with LAT-TD-04350 and PRC_Pi_QC_005. This document is compiled and reviewed within the Tracker subsystem prior to shipment of the tower from INFN to SLAC. The contents of this document have been coordinated between LAT Integration, Test, and Calibration (IT&C), LAT Systems Engineering (SE), LAT Quality Assurance (QA), and the TKR subsystem.
Note: tracker tower 16 is a non-flight module as many non-flight parts were used for its integration (see NCR/FM/INFN/PI-593) and environmental tests were not performed. This document serves for traceability purposes
Item Description: |
||
Identification |
Part/Drawing
Number |
Serial
Number |
|
LAT-DS-00722 |
16 |
Cable holding plate |
LAT-DS-03826 |
NA |
LAT-DS-03949 |
NA |
MECHANICAL
SUMMARY DATA |
Mechanical Lead: E. Rapposelli |
|
|
ITEM: |
REMARKS: |
|
Structural Analysis
reviewed and acceptable |
Available on file at SLAC |
|
Structural Tests reviewed
and acceptable |
Available on file at SLAC |
|
Open Items from tests performed or
from meetings with SLAC |
None |
|
Mass (measured) |
32.820 Kg |
|
Mass / Center of Mass Report -
Analysis |
Mass / CoM report |
|
Dimensions |
Complies with IDD |
|
Interface flatness and surface finish |
Complies with IDD |
|
Dimension Inspection Report |
|
|
Final visual inspection prior to
shipping |
Tower Flow-chart on file at INFN-Pisa
(summary) |
ELECTRICAL
SUMMARY DATA |
Electrical Lead: Luca Latronico |
|
|
DESCRIPTION: |
REMARKS: |
|
Power consumption (28V, 25 deg C,
nominal activity) TKR + TEM/TPS |
19.6W |
|
Power consumption (AVVDA, AVDDB,
DVDD, 25 C, nominal Activity) |
NA |
|
Overall leakage current at 100V |
NA |
|
Part List reviewed and acceptable |
Tower Flow-chart on file at INFN-Pisa
|
|
Pre-ship electrical Test reviewed and
acceptable |
Available on file at INFN-Pisa |
|
Open Items from previous reviews /
meetings / tests |
Status of channels history (link) |
|
Relevant support documents |
Standard schema (xml archive) Tower Map (link)
|
PRODUCT
ASSURANCE DATA |
Quality Lead Engineer: Aldo
Troianiello |
|
|
DESCRIPTION: |
REMARKS: |
|
Non-conformance report summary |
NCR summary (link) |
|
Open NCRs /
RFW / RFD |
NA |
|
Traceability of unit pedigree |
Tower Flow-chart on file at INFN-Pisa |
|
Photographic Record |
NA |
|
Inspection records |
Tower Flow-chart on file at INFN-Pisa
|
|
Storage, handling, shock records |
On file at INFN-Pisa |
|
WOA list |
Tower Flow-chart and procedural
travelers therein – available on file at INFN-Pisa |
|
All operations, inspections, and tests
have been completed per procedures as indicated on WOA (signed and dated) |
Tower Flow-chart and procedural
travelers therein – available on file at INFN-Pisa |
|
All operations performed to released
and controlled procedures |
Procedures available on file at SLAC
and INFN-Pisa |
|
Chronological history is up-to-date
and reflects each major action that has transpired |
Tower Flow-chart on file at INFN-Pisa |
|
Identity of manufacturers, part numbers,
and serial number are correct |
Tower Flow-chart on file at INFN-Pisa |
|
All Problem Reports, Material Review
Board Reports, and failure reports are closed and accepted as per internal
procedures |
NCR database available on file and on
web at INFN-Pisa |
|
Materials and processes used in the
hardware are approved and acceptable |
Materials and processes under
configuration control at SLAC |
|
Test logbooks, including operating
time and cycle records, are complete and meet specified requirements |
Log books on file at INFN-Pisa |
|
All test data including deviations
have been approved and stamped by the test engineer and Quality Assurance |
Tower Flow-chart on file at INFN-Pisa |
|
Inspection performed for physical damage
(such as scratches or dents) and for cleanliness |
Tower Flow-chart on file at INFN-Pisa |
|
Connectors and pins examined for
evidence of damage or contamination |
No evidence of damage or
contamination. Refer to Mate/Demate Log |
|
All environmental test data and
results meet specifications |
Environmental test reports |
The LAT Tracker Test Verification Matrix, LAT-SS-04126, summarizes the requirements and verification method contained in:
LAT-SS-00017 TKR Subsystem Specification
LAT-SS-00134 LAT-TKR Detailed Subsystem
Specification
LAT-SS-00138 TKR-LAT Mech., Thermal Interface
Control Doc.
LAT-SS-00152 LAT Readout Electronic
Specification
LAT-SS-00176 TKR-LAT Electrical Interface
Control Doc.
LAT-SS-00778 LAT Environmental Specification
The verification status and/or data product mapping is indicated in the current release of the document
The TKR Comprehensive Performance Test (CPT) is defined in LAT-TD-00191.
Phase |
Test |
Date |
Summary Status |
Egse Test Session Report |
Initial Test |
CPT |
|
Pass |
|
Preship |
CPT |
|
Pass |
|
NA
NA
Offline analysis of alignment and efficiency report.
See (link) for status of channels. Calibration data for ToT and efficiencies will be collected at SLAC
Phase |
Test |
LATTE Release |
TKR EGSE Release |
Initial Test |
CPT |
P04-05-00 |
V5-p1 |
Post Vibration Test |
CPT |
P04-06-03 |
V4-p4-pisa-1-3 |
Post TVAC/Pre-Ship Test |
CPT |
P04-06-03 |
V4-p4-pisa-1-3 |
NA
NA