Document # |
Date Effective |
|
LAT-TD-05920 |
|
|
Prepared by(s) |
Supersedes |
|
L.
Latronico H. Tajima R.
Johnson |
|
|
GLAST LAT Technical
Note |
|
|
Subsystem/Office |
||
Tracker Subsystem |
||
Document Title |
||
Gamma-ray Large Area Space Telescope (GLAST)
Large Area Telescope (LAT)
Tracker Subsystem
End Item Data Package
Tower B
DOCUMENT APPROVAL
Prepared
by: |
|
|
|
|
|
L. Latronico |
|
Date |
Approved by: |
|
|
|
|
|
E. Rapposelli |
|
Date |
|
|
|
L. Latronico |
|
Date |
|
|
|
N. Mazziotta TKR Subsystem Environmental Test Lead Engineer |
|
Date |
|
|
|
A. Troianiello |
|
Date |
|
|
|
Robert P. Johnson |
|
Date |
|
|
|
A. Brez |
|
Date |
LAT Acceptance
|
|
|
Dick Horn |
|
Date |
|
|
|
Pat Hascall |
|
Date |
|
|
|
Elliott Bloom |
|
Date |
|
|
|
Darren Marsh |
|
Date |
|
|
|
Other |
|
Date |
CHANGE HISTORY LOG
Revision |
Effective Date |
Description of
Changes |
01 |
|
Initial Draft |
02 |
|
Update with post-ship information |
|
|
|
|
|
|
|
|
|
The purpose of this document is to collect all the data for the Glast LAT Tracker (TKR) Tower End Item Data Package (EIDP), in compliance with LAT-TD-04350 and PRC_Pi_QC_005. This document is compiled and reviewed within the Tracker subsystem prior to shipment of Tower A from INFN to SLAC. The contents of this document have been coordinated between LAT Integration, Test, and Calibration (IT&C), LAT Systems Engineering (SE), LAT Quality Assurance (QA), and the TKR subsystem.
Item Description: |
||
Identification |
Part/Drawing
Number |
Serial
Number |
|
LAT-DS-00722 |
B |
Cable holding plate |
LAT-DS-03826 |
NA |
LAT-DS-03949 |
NA |
MECHANICAL
SUMMARY DATA |
Mechanical Lead: INFN: E. Rapposelli SLAC: D.
Rich |
|
|
ITEM: |
REMARKS: |
|
Structural Analysis reviewed
and acceptable |
Available on file at SLAC |
|
Structural Tests reviewed
and acceptable |
Available on file at SLAC |
|
Open Items from tests performed or
from meetings with SLAC |
None |
|
Mass (measured) |
32.640 kg |
|
Mass / Center of Mass Report -
Analysis |
Mass / CoM report |
|
Dimensions |
Complies with IDD |
|
Interface flatness and surface finish |
Complies with IDD |
|
Dimension Inspection Report |
|
|
Final visual inspection prior to
shipping |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Tower receiving, EMI taping, and test
at SLAC |
|
|
Tower B Verification Matrix |
ELECTRICAL
SUMMARY DATA |
INFN Electrical Lead: |
SLAC Electrical Lead: Hiro Tajima |
|
|
DESCRIPTION: |
REMARKS: |
|
|
Power consumption (28V, 25 deg C,
nominal activity) TKR + TEM/TPS |
18 W |
16.5 W (21.6 deg C) |
|
Power consumption (AVVDA, AVDDB,
DVDD, 25 C, nominal Activity) |
10.0 W |
9.8 W (21.6 deg C) |
|
Part List reviewed and acceptable |
Tower Flow-chart on file at INFN-Pisa
(summary) |
N/A |
|
Pre-ship electrical Test reviewed and
acceptable |
Available on file at INFN-Pisa |
N/A (See below for
post-shipping and hand-off test results.) |
|
Open Items from previous reviews /
meetings / tests |
Status of channels history (link) |
Status of
channels history (link) |
|
Relevant support documents |
Standard schema file (xml archive) Tower Map (link) |
Standard schema files (xml
archive) |
PRODUCT
ASSURANCE DATA |
Quality Lead Engineer: Aldo
Troianiello |
|
|
DESCRIPTION: |
REMARKS: |
|
Non-conformance report summary |
NCR summary (link) |
|
INFN Tower-B NCRs |
Summary (link). Closure
Status at Handoff |
|
SLAC Tower-B NCRs |
Summary
(link) |
|
Traceability of unit pedigree |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Photographic Record |
On file at INFN-Pisa (link) Tower receiving at SLAC (link) |
|
Inspection records |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Storage, handling, shock records |
On file at INFN-Pisa |
|
WOA list |
Tower Flow-chart and procedural
travelers therein – available on file at INFN-Pisa |
|
All operations, inspections, and
tests have been completed per procedures as indicated on WOA (signed and
dated) |
Tower Flow-chart and procedural
travelers therein – available on file at INFN-Pisa |
|
All operations performed to released
and controlled procedures |
Procedures available on file at SLAC
and INFN-Pisa |
|
Chronological history is up-to-date and
reflects each major action that has transpired |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Identity of manufacturers, part
numbers, and serial number are correct |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
All Problem Reports, Material Review
Board Reports, and failure reports are closed and accepted as per internal
procedures |
NCR database available on file and on
web at INFN-Pisa |
|
Materials and processes used in the
hardware are approved and acceptable |
Materials and processes under
configuration control at SLAC |
|
Test logbooks, including operating time
and cycle records, are complete and meet specified requirements |
Log books on file at INFN-Pisa |
|
All test data including deviations
have been approved and stamped by the test engineer and Quality Assurance |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Inspection performed for physical
damage (such as scratches or dents) and for cleanliness |
Tower Flow-chart on file at INFN-Pisa
(summary) |
|
Connectors and pins examined for
evidence of damage or contamination |
No evidence of damage or
contamination. Refer to Mate/Demate Log |
|
All environmental test data and
results meet specifications |
Environmental test reports,
see below. |
ENVIRONMENTAL TEST
SUMMARY DATA |
System Engineer: Tom Himel |
||||
EMI/EMC Test |
Test Procedure: LAT-TD-05462 |
||||
Summary Report |
|||||
Requirement |
Criteria |
Pass / Fail |
|||
Acceptance Test |
LAT-SS-00778 Sect 13 |
Flight Acceptance |
Pass |
||
ENVIRONMENTAL TEST
SUMMARY DATA |
System Engineer: Nicola Mazziotta |
|
|||
Vibration Test |
LAT-TD-00155 (Test Plan) and LAT-TD-05499 (Test Procedure) |
|
|||
Summary Report |
LAT-TD-05777 |
|
|||
Requirement |
LAT-MD-00408 and
LAT-SS-00778 Criteria |
Pass / Fail |
|
||
Static-Equivalent Acceleration |
LAT-SS-00778 Sect 8.1 Tab 3 |
Flight (FM) |
Pass |
||
Random Vibration |
LAT-SS-00778 Sect 9.1 Tab 20 |
Flight (FM) |
Pass |
||
Sinusoidal Vibration |
LAT-SS-00778 Sect 9.2 Tab 24 |
Flight (FM) |
Pass |
||
CPT |
LAT-MD-00408, Sect 7.1.2.1.1
|
Prior and after |
Pass |
||
ENVIRONMENTAL TEST SUMMARY
DATA |
System Engineer: Nicola Mazziotta |
||
Thermal Vacuum Test |
LAT-TD-01840 (Test Plan) and LAT-TD-05500 (Test Procedure) |
||
Summary Report |
LAT-TD-05778 |
||
Requirement |
LAT-MD-00408 and
LAT-SS-00778 Criteria |
Pass / Fail |
|
Acceptance Temperature |
Max/Min Predict ± 5 °C LAT-MD-00408, Sect 5 Tab 5-2 |
–15 °C to +45 °C (FM) |
Pass |
Acceptance Survival Temperature |
Max/Min Predict ± 5 °C LAT-MD-00408, Sect 5 Tab 5-2 |
–15 °C to +45 °C (FM) |
Pass |
Acceptance Operational Temperature |
Max/Min Predict ± 5 °C LAT-MD-00408, Sect 5 Tab 5-2 |
–15 °C to +45 °C (FM) |
Pass |
Hot Turn On |
LAT-MD-00408, Sect 7.1.2.7 LAT-TD-05500, Sect 8 |
+45°C |
Pass |
Cold Turn On |
LAT-MD-00408, Sect 7.1.2.7 LAT-TD-05500, Sect 8 |
–15°C |
Pass |
Bakeout test |
LAT-MD-00408, Sect 7.1.2.7 LAT-TD-05500, Sect 8.2.2 |
+45°C |
Pass |
Number of thermal cycles |
LAT-MD-00408, Sect 5 Tab 5-2 LAT-TD-05500, Sect 8 |
4 |
Pass |
CPT |
LAT-MD-00408, Sect 7.1.2.1.1 LAT-TD-05500, Sect 7.5.2 |
Prior, during and after |
Pass |
Functional/LPT |
LAT-MD-00408, Sect 7.1.2.1.2 LAT-TD-05500, Sect 7.5.1 LAT-TD-05500, Sect 7.5.3 |
During |
Pass |
The LAT Tracker Test Verification Matrix, LAT-SS-04126, summarizes the requirements and verification method contained in:
LAT-SS-00017 TKR Subsystem Specification
LAT-SS-00134 LAT-TKR Detailed Subsystem
Specification
LAT-SS-00138 TKR-LAT Mech., Thermal Interface
Control Doc.
LAT-SS-00152 LAT Readout Electronic
Specification
LAT-SS-00176 TKR-LAT Electrical Interface
Control Doc.
LAT-SS-00778 LAT Environmental Specification
The verification status and/or data product mapping is indicated in the current release of the document
The TKR Comprehensive Performance Test (CPT) is defined in
LAT-TD-00191.
Phase |
Test |
Date |
Summary Status |
Egse Test Session Report |
Initial Test |
CPT |
|
Pass |
|
Post EMI/EMC |
CPT |
NA |
NA |
NA |
Post Vibration Test |
CPT |
|
Pass |
|
Post TVAC Test |
CPT |
|
Pass (in
vacuum @ room temperature) |
|
Pre-ship Test |
CPT |
|
Pass (leakage
current measurement only) |
|
Post-Ship Test |
CPT |
|
pass |
Go to Shift Run Info and
search run range 398000653-398000688 |
Hand-Off Test |
PS-05481 |
|
pass |
Go to Shift Run Info
and search run range 398000702-398000799 |
Trend Analysis |
Efficiency |
|
|
Dead time (TE703) and Noise Occupancy during Readout (TE704) will be measured during I&T phase using GASU based system.
NA
See (link Pisa) for status of channels (link SLAC) and efficiency (link SLAC).
Calibration data (xml archive)
Phase |
Test |
LATTE Release |
TKR EGSE Release |
Initial Test |
CPT |
P04-05-00 |
V4-p4-pisa-1-2 |
Post Vibration Test |
CPT |
P04-05-00 |
V4-p4-pisa-1-2 |
Post TVAC Test |
CPT |
P04-05-00 |
V4-p4-pisa-1-2 |
Preship Test |
CPT |
P04-05-00 |
V4-p4-pisa-1-2 |
Post-ship Test |
CPT |
P04-06-04 |
v5p5 |
Handoff Test (LAT-PS-05481) |
All |
P04-06-04 |
v5p5 |
Link to Mate / De-mate Log: TKR TowerA Mate Demate Log (Note: mate/demate log on trays to be provided from G&A)
Operational hours at